Debris removal in the back lot continues, and the crew from Foss Demolition anticipates that this should be completed by the end of next week. Soon, you will begin to see truckloads of dirt coming to begin leveling off this land!

 

 

Framing work for the three new bathrooms (two in the narthex, one between the Commons and the conference room) has begun!

Work on the boiler room continued this week, as footers were being placed and poured for the construction of the room. A temporary wall has been built in the Bridal Suite nursery to make safe and straightforward the internal work that will need to be done on the new boiler room space.